Tilt-Up Concrete Construction
Site
Evaluation
Planning begins with an evaluation of
the site. A large, flat, open site is
ideal, but not common. Therefore,
evaluate the site with regard to slab
layout and the movement of materials and
equipment around the slab. If the site
is tight around the building, consider
sequencing the pouring of slabs and
panels from within the building.
A plan or sketch showing the pouring and
erection sequence relative to the site
and floor plan of the building can
identify potential problems.